Press - News
Archive
Press - News
Archive
Press - News
Archive

At the beginning of November 2011 Mostostal Puławy begun the assembling of power boiler with fluidized bed in a thermal power plant in Kyröskoski, Finland. The scope of work includes: complete mechanical assembly of the boiler (pressure part, exhaust ducts and air, external piping and other equipment).

Pressure test of the boiler was planned in March 2012. The investment is to be completed in July 2012.

Assembly of a power boiler with fluidized bed in Kyröskoski, FinlandAssembly of a power boiler with fluidized bed in Kyröskoski, Finland