On 29 August 2011 Mostostal Puławy S.A. started installation of a steam boiler equipped with a grate furnace fired with wood (OSr-32 type) in the city of Goch in Germany. The scope of works covers installation of the boiler and piping within the boiler building. The principal of the task is Rafako. The approximate total weight of the entire scope of works is 382 t. The water test is expected to be performed on 12 December 2011. The installation completion date is 15 January 2012.