Mostostal Puławy S.A. has been commissioned with an assembling of a CFB boiler (460MWt, 160/143 kg/s, 164/43 bar(a), 560/560°C). The order was made by Foster Wheeler Energia Oy.
The assembling of the boiler would be carried out in Jyväskylä, Finland (about 270km North of Helsinki). Jyväskylän Energia Oy is the investor.

 

The beginning of works is planned on August 4th,2008 and the finish on August 20th, 2009, and the pressure test would be carried out on March 13, 2009. The end delivery would be in 2010. The scope of works for Mostostal Puławy contains complex mechanical assembly of a boiler with the belonging devices and rotating air heater.