On May, 2010 Mostostal Pulawy is beginning a new realization – the construction of a boiler in the incineration plant in Linz. The agreement has been signed on April 9th, 2010. The waste heat boiler’s efficiency is 130 tonnes of steam/h, 58 bar working pressure.
Additionally our company will install the pipelines, channels, cyclones and the appliances in the incineration plant (aggregates, fans, tanks). Total weight of the elements is 1432 tonnes.
The realization is going to be finished on March, 2011.